B. Software Development · Software Development: Managing a Team Software Project

Work Breakdown, Deliverables, Estimates and Risks

B1.1 B1.4About 75 minutes
Learning goals
  • I can break a project into a work breakdown structure (WBS) of deliverables and work packages.
  • I can tell the difference between a task, a deliverable and a milestone.
  • I can estimate tasks with three-point (PERT) estimates, including a standard deviation, and combine them for a whole project.
  • I can convert effort (person-hours) into calendar time using real availability.
  • I can build a risk register that scores risks by probability and impact and plans a response for each.

Words to know

work breakdown structure (WBS)
A tree that splits the project's total work into deliverables and then into small work packages. Together the leaves cover 100% of the work.
work package
A leaf of the WBS: a piece of work small enough to estimate, schedule and give to one owner.
milestone
A checkpoint with no length of its own, such as "scope signed" or "version 1.0 delivered".
effort
The amount of work, in person-hours. Two people working 3 hours each is 6 person-hours.
duration
The calendar time a task takes, which depends on effort, how many people work on it and how many hours they are available.
three-point estimate
An estimate with an optimistic (O), most likely (M) and pessimistic (P) value. PERT expected time is (O + 4M + P) ÷ 6 and its standard deviation is (P − O) ÷ 6.
risk
Something that might happen and would harm the project if it did. A risk has a probability and an impact.
risk register
A table of risks with their probability, impact, score, response, owner and warning sign (trigger).

"How long will it take?"

Every client asks it, and every honest developer finds it hard to answer. The trick is not to guess the whole project at once. You break the work into small pieces, estimate each piece (with a range, not a single number), add them up carefully, and then ask what could go wrong.

This lesson finishes the planning deliverables named in B1.1: the tasks, the deliverables and the information you need for the schedule (which the next lesson draws as Gantt and PERT charts).

The work breakdown structure

A work breakdown structure (WBS) is a tree. The root is the whole product. The next level is the big deliverables or phases. Each of those is split again until every leaf is a work package: a piece of work that one person can own and finish in a few hours to a couple of days.

Two rules make a WBS useful:

  • The 100% rule. The leaves together cover all the work, including the unglamorous parts: planning, testing, documentation, installation, training, the final review. If it is not in the WBS, it is not in the schedule, and it will be done at midnight.
  • Small enough to estimate. For a student project, a work package should be roughly 1 to 8 hours of effort. A leaf like "write the program" is far too big to estimate honestly.

Numbering (1, 1.1, 1.2, ...) lets you refer to work packages in the schedule, status reports and the Git commit messages you will write later.

LendIt 1.01 Planning1.1 Interview1.2 Scope doc1.3 Schedule2 Design2.1 Data design2.2 Interfaces2.3 Menu design3 Code3.1 Items3.2 Loans3.3 Storage3.4 Menu4 Test4.1 Test plan4.2 Unit tests4.3 Integration4.4 Acceptance5 Deliver5.1 User guide5.2 Training5.3 Install5.4 Support plan6 Close6.1 Sign-off6.2 ReviewEach leaf is a work package small enough to estimate and give to one owner.
LendIt's WBS: six deliverable groups and 20 work packages (3.1 to 3.4 are the four code modules). Notice that testing, documentation, delivery and closing are planned work, not afterthoughts.

Tasks, deliverables and milestones

These three words are easy to mix up:

  • A task (work package) is work: "3.2 write the loans module". It takes time and has an owner.
  • A deliverable is a thing handed over: the loans module itself, the test report, the user guide. Some deliverables go to the client (the program, the guide); some are internal (the design document).
  • A milestone is a moment: "code complete", "scope signed". It has zero duration and marks the end of a group of tasks.

A good plan lists all three, and every deliverable has a task that produces it and a milestone by which it is due.

Estimating with three points

In ICS3U you used PERT to combine three estimates into an expected time:

E = (O + 4M + P) ÷ 6

PERT also gives a measure of uncertainty, the standard deviation:

σ = (P − O) ÷ 6

A wide gap between the optimistic and pessimistic estimates means a big σ: you are not sure. When independent tasks are done one after another, you add their expected times and add their variances (σ²), then take the square root to get the total σ. You add variances, not standard deviations, for the same reason as in MDM4U's probability units: independent ups and downs partly cancel out.

Estimates should be made by the person who will do the work, after looking at similar past work. Two well-known traps: people are usually too optimistic about their own tasks, and they forget work that is not coding (meetings, reviews, fixing tests).

Worked example

Example 1: Estimating the coding tasks

Jordan gives three-point estimates (in hours) for LendIt's four coding work packages: items module O = 4, M = 6, P = 10; loans module O = 6, M = 8, P = 16; storage module O = 3, M = 5, P = 13; menu O = 4, M = 6, P = 8. Find each expected time and σ, then the total expected time and its σ.

  1. Items: E = (4 + 24 + 10) ÷ 6 = 38 ÷ 6 ≈ 6.33 h; σ = (10 − 4) ÷ 6 = 1.00 h.
  2. Loans: E = (6 + 32 + 16) ÷ 6 = 54 ÷ 6 = 9.00 h; σ = 10 ÷ 6 ≈ 1.67 h.
  3. Storage: E = (3 + 20 + 13) ÷ 6 = 36 ÷ 6 = 6.00 h; σ = 10 ÷ 6 ≈ 1.67 h.
  4. Menu: E = (4 + 24 + 8) ÷ 6 = 36 ÷ 6 = 6.00 h; σ = 4 ÷ 6 ≈ 0.67 h.
  5. Total E = 38/6 + 9 + 6 + 6 ≈ 27.33 h.
  6. Variances: 1² + (10/6)² + (10/6)² + (4/6)² = 1 + 100/36 + 100/36 + 16/36 = 1 + 216/36 = 1 + 6 = 7. Total σ = √7 ≈ 2.65 h.

About 27.3 hours of coding effort, give or take about 2.6 hours (one standard deviation). Planning for about E + 2σ ≈ 32.6 hours gives a comfortable margin.

The same calculation as a program. The f-string {name:<20} pads the name to 20 characters on the left, and {e:6.2f} prints the number in 6 spaces with 2 decimals, so the columns line up.

import math
tasks = [("3.1 Items module", 4, 6, 10),
("3.2 Loans module", 6, 8, 16),
("3.3 Storage module", 3, 5, 13),
("3.4 Menu", 4, 6, 8)]
total_e = 0
total_var = 0
for name, o, m, p in tasks:
e = (o + 4 * m + p) / 6
sd = (p - o) / 6
total_e += e
total_var += sd ** 2
print(f"{name:<20}{e:6.2f} h sd {sd:4.2f}")
print(f"{'Total':<20}{total_e:6.2f} h sd {math.sqrt(total_var):4.2f}")

Output: one line per task (6.33, 9.00, 6.00 and 6.00 hours with standard deviations 1.00, 1.67, 1.67 and 0.67), then the total line: 27.33 h with sd 2.65. The total sd is the square root of the sum of the variances, not the sum of the sds (which would be 5.00).

From effort to calendar time

An estimate in person-hours (effort) is not a date. To schedule, convert to duration using how much time people really have.

The LendIt team has about 5 class hours a week on the project, plus about 2 hours each of homework, but some class time goes to meetings and other subjects interrupt. Priya counts 5 productive hours per person per week, so the team has about 4 × 5 = 20 person-hours a week.

The four coding packages total about 27 to 33 hours. Split between two developers working in parallel, that is roughly 14 to 17 hours each, or about 3 weeks at 5 hours a week. One person alone would need about 6 weeks. That is why the work must be split, and why the split must be planned (the next lesson's critical path shows which tasks can run in parallel).

Risks and the risk register

A risk is something that might happen and would hurt the project. (Something that has already happened is an issue.) For each risk, estimate:

  • Probability: 1 (unlikely), 2 (possible), 3 (likely).
  • Impact: 1 (minor delay), 2 (serious delay or a feature lost), 3 (project fails or data is lost).
  • Score = probability × impact, so the biggest risks get attention first.

Then choose a response:

  • Avoid: change the plan so the risk cannot happen (check the laptop's Python version in week 1).
  • Reduce (mitigate): make it less likely or less harmful (two people know every module; back up data).
  • Transfer: make someone else responsible (the centre's IT volunteer handles the laptop).
  • Accept: live with it, but watch for its trigger (warning sign).

Every risk gets an owner who watches it.

IDRiskPIScoreResponseOwner
K1A member is sick for several days224Reduce: commit work daily to the shared repository; every module has a second person who reviews itPriya
K2The centre's laptop has an old Python version236Avoid: check the version in week 1 and code to itJordan
K3The loan data file is damaged133Reduce: write to a temporary file, then rename; keep daily backupsJordan
K4Denise is away during acceptance week224Reduce: book the acceptance meeting date in week 1Priya
K5The loans module takes much longer than estimated326Reduce: start it first; use the PERT estimate plus a buffer; review progress at each stand-upJordan
LendIt's risk register (P = probability, I = impact, each 1 to 3).
3692461231 low2 medium3 highProbability3 high2 medium1 lowImpactK1K2K3K4K5K1 member sick for daysK2 old Python on laptopK3 loan file damagedK4 client away at the endK5 loans module underestimatedscore = probability × impact
The same risks on a probability-impact grid. The number in the corner of each cell is its score. K2 and K5 have the highest scores (6), so they get attention first. No LendIt risk is in the 9 cell.
Worked example

Example 2: Ranking and responding

Rank LendIt's risks by score. Then suggest a trigger (warning sign) for K5 and say what the team will do if it appears.

  1. Scores: K1 = 2 × 2 = 4; K2 = 2 × 3 = 6; K3 = 1 × 3 = 3; K4 = 2 × 2 = 4; K5 = 3 × 2 = 6.
  2. Ranked: K2 and K5 (6), then K1 and K4 (4), then K3 (3).
  3. Trigger for K5: at the end of week 3 the loans module is less than half done, or its tests are still failing.
  4. Planned action: move Luc from documentation to help with loan tests for two days, and tell Denise at once if a Should requirement (R7, the 3-item limit) has to move to a later version.

Order: K2, K5, K1, K4, K3. A trigger turns a vague worry into a specific check the team does at a set time.

Sorting a risk register by score is a one-line job in Python. The key=score argument tells sorted to compare risks by their scores. Python's sort is stable: risks with equal scores stay in their original order.

risks = [("K1 member sick for days", 2, 2),
("K2 old Python on laptop", 2, 3),
("K3 loan file damaged", 1, 3),
("K4 client away at the end", 2, 2),
("K5 loans module underestimated", 3, 2)]
def score(risk):
return risk[1] * risk[2] # probability x impact
for r in sorted(risks, key=score, reverse=True):
print(score(r), r[0])

Output: 6 K2 old Python on laptop / 6 K5 loans module underestimated / 4 K1 member sick for days / 4 K4 client away at the end / 3 K3 loan file damaged (one line each)

Just for fun

Hofstadter's Law, from Douglas Hofstadter's 1979 book Gödel, Escher, Bach: "It always takes longer than you expect, even when you take into account Hofstadter's Law." Every project manager has tested it. It has never failed.

Hands-on activity

Project step 3: Break down, estimate and worry (productively)

You need: your scope document, sticky notes or paper slips, and a pencil.

  1. Build your WBS with sticky notes: write the project name on one note, then 4 to 6 deliverable groups (planning, design, code, test, deliver, close), then work packages under each. Keep splitting until each one is 1 to 8 hours of work. Check the 100% rule: is testing there? Documentation? Training your client?
  2. Number every work package (1.1, 1.2, ...).
  3. Estimate each coding package with O, M and P (in hours). Use the estimate program from this lesson to get E and σ for each and the total.
  4. Convert to calendar time: how many hours a week can you (and each teammate) really give? Divide.
  5. Write a risk register with at least 5 risks, including one about people, one about technology and one about data. Score them and give each a response, owner and trigger.
  6. Save it all as docs/plan.md in your project folder (photograph the sticky-note WBS and save the picture in docs, too).

What to look for: no work package bigger than a day; testing and documentation in the WBS; an honest weekly availability; responses that are actions, not hopes ("start the hard module first", not "work hard").

Your turn

1

What is the 100% rule of a WBS?

2

Classify each as a task, deliverable or milestone: (a) user guide; (b) write the storage module; (c) scope signed; (d) test report; (e) code complete.

3

A task has O = 2, M = 5, P = 14 hours. Find E and σ.

4

Two tasks done one after the other have σ = 3 h and σ = 4 h. What is the σ of the total?

5

A task needs 12 person-hours. Two people each have 3 hours a week for it. About how many weeks will it take?

6

Score a risk with probability 3 and impact 1, and one with probability 1 and impact 3. Which comes first in the sorted register?

7

Give the four kinds of risk response.

More practice: warm-up

1

What does WBS stand for?

2

What is the PERT formula for expected time?

3

What is the difference between a risk and an issue?

4

Find σ for O = 3, M = 4, P = 9.

5

What is the score of a risk with probability 2 and impact 3?

More practice: on your own

1

Why is "write the program" a poor work package?

2

The loans module's pessimistic estimate rises from 16 to 22 hours (O = 6, M = 8). Find the new E and σ. What does the larger σ tell the PM?

3

Suggest a response and a trigger for this risk: "The client changes their mind about the main menu late in the project."

4

In the estimate program, what would the total line show if the sds were added instead of the variances?

5

Priya's team has 20 person-hours per week. The WBS totals 110 hours of expected effort, and she wants a margin of 15%. How many weeks should she plan?

Challenge

1

Using the total from Example 1 (E ≈ 27.33 h, σ ≈ 2.65 h) and the normal approximation from MDM4U, estimate the probability that the coding takes more than 32.6 hours.

2

Modify the risk program so that it prints only risks with a score of 4 or more, each with the word HIGH if the score is 6 or more. Write the new loop.

3

Explain why adding more people to a late task does not always shorten it in proportion. Give two reasons from software work.

Check your understanding

Quiz

1.

Which is a milestone?

2.

A task has O = 1, M = 4, P = 13 hours. What is its PERT expected time?

3.

Two independent tasks in sequence have σ = 6 h and σ = 8 h. What is the σ of their total?

4.

Which risk response is "check the laptop's Python version in week 1 and code to it"?

5.

What does the 100% rule say?

6.

A risk has probability 3 and impact 2. What is its score on a 1-to-3 scale for each?

For parents and teachers

Big idea: This lesson completes the planning parts of B1.1 (tasks, deliverables and the information needed for a schedule) and starts B1.4 (project management tools). Students build a work breakdown structure, make three-point estimates with a standard deviation (connecting to MDM4U statistics), convert effort into calendar time, and write a risk register.

How to help: Ask your teen how many hours a week they really have for this project, given school, work and activities; honest availability is the most common gap in student plans. Look at their risk register and ask "What's the warning sign, and what will you do when you see it?"

Common difficulties:

  • Work packages that are far too big ("code everything").
  • Leaving out testing, documentation and training from the WBS.
  • Adding standard deviations instead of variances when combining estimates.
  • Risk responses that are hopes ("be careful") rather than actions ("save a backup every day").